Planning and design of annual output of 100,000 cubic meters production line
Planning and design of annual output of 100,000 cubic meters Aac production line
1. The site area is about 20 mu, including raw material storage area, finished product storage area, and process flow area.
The equipment covers an area of 10 mu.
2. The production process is divided into raw material processing, pouring, metering and mixing, hot chamber static stop pre-curing, cutting, marshalling, steaming
Pressure maintenance and other processes.
3. From civil construction to equipment installation, commissioning, trial production and commissioning, the period is 3 to 5 months.
4. Steel structure design of the main workshop: about 1500m2
5. Personnel: Raw material processing, pouring, metering and mixing, hot room static stop pre-curing, cutting, grouping into single-shift production,
The autoclave and boiler sections work in three shifts. A total of 16~18 people are needed. Including management personnel, about 22-30 people are needed
right.